Integrated Lift Solutions complete second lift at the Sainsbury’s car park at the Forum in Horsham.

Sainsburys

Integrated Lift Solutions were asked to;

  • Extend hoardings to accommodate new openings.
  • Disconnect electrical supply to existing lift
  • Remove  7 storey lift and all associated components & discard off site
  • Supply and erect Cuplok scaffolding and dismantle upon completion. 21m high, 2 metre lifts approximately 1300 x 1300mm square c/w internal ladder access.
  • Remove  brickwork to accommodate new lift entrances on 5nr floors
  • Fix medium density fibreboard linings to cover gap between new frame and existing finishes
  • Fix skirting and architraves to match existing
  • Infill between new architraves and existing shaft walls in timber stud work clad with 15mm fire-line board
  • Making good to reveals including paint and decoration
  • Make good to vinyl tiles using contrasting colours

 

For more information on Building Services for the Lift Industry, call 01484 303204 or complete our free survey form below.

Free Survey

 

Thank you for contacting Integrated Lift Solutions.
A member of our team will contact you in the next 2 working days.